Concord Avenue Paving Commences Thursday, Oct. 1 at 6 AM

Photo: Road work on Concord Avenue.

Final preparations and paving of Concord Avenue from the intersection of Cottage Street to the US Postal Service office will begin Thursday, Oct. 1, at 6 a.m., according to Belmont town officials.

The contractor believes it will take a single day to complete the paving.

Also, Cottage Street from Concord Avenue to School Street will also be paved by contractor E.H. Perkins Construction.

Concord Avenue will be open for traffic during the prep work and paving. All vehicles will travel on either side of the roadway during the working hours as delineated by traffic cones. 

Cottage Street may be briefly unavailable to homeowners when the asphalt is being laid.

On-street parking on both sides of Concord Avenue will not be allowed from Goden Street to the intersection of Common Street.

The work on Concord Avenue is part of the $2 million 2015 Pavement Managment program. 

Residents with questions or concerns about the project can contact Robert Bosselman, the engineer in the Office of Community Development, at 617-993-2650.

Concord Avenue Repair To Take A Bit Longer Than Expected

Photo: It’s a mess on Concord Avenue.

Monday’s commute via Concord Avenue was a “hurry-up-and-wait” experience as the surface of both sides of the main thoroughfare from Cambridge and Belmont High School to Belmont Center and points west were being ripped out, leaving a lunar landscape between Cottage Street and Common Street.

The reconstruction of the roadway, part of the annual Pavement Management Program, resulted in a monumental bottleneck this morning at the intersection of Goden Street where four lanes was reduced to two with many vehicles turning across both reduced traffic lanes.

And now it appears the work will take a bit longer than initially expected.

IMG_1888

According to Town Engineer and Director of Community Development Glenn Clancy, contractor E.H. Perkins Construction informed him that the pulverization of the roadway “is slower than expected due to field conditions such as asphalt thickness and other factors.” 

Clancy said Perkins is aiming for the middle to the end of this week for it to put a surface “binder” on both sides of Concord Avenue and onto Cottage Street.

That time frame could be affected by a forecast of two days of heavy rain beginning Tuesday, Sept, 29, which will leave the surface too wet to apply the asphalt. 

Stay tuned.