Night Moves: Trapelo Road Paving Begins Monday 7 PM

Work on the Trapelo/Belmont Corridor Project goes under the lights next week as the repaving of Trapelo Road from Mill Street to the Belmont Car Wash and the “triangle” encompassing Lexington and Church streets in Waverley Square begins Monday evening, July 28 at 7 p.m.

While the Massachusetts Department of Transportation – the $17 million roadway construction is a state project – and the project contractor were set begin work this week, the Belmont Board of Selectmen Monday, July 21, pushed back the starting date five days to allow residents along the route time to prepare for three days of 12 hours of construction outside their front doors.

According to Tony Barrile, vice president of operations for project contractor Newport Construction of Nashua, NH, the combination of high temperatures, heavy commuter traffic and the narrowness of the roadway would lead to chaotic conditions performing the job during the work day.

Answering questions concerning the MDOT’s request to proceed with night work, Barrile said the new asphalt must cool after being laid forcing traffic on a single lane at certain choke points near the Shaw’s Supermarket on Trapelo Road, impacting rush hour traffic in the morning and afternoon, resulting in lengthy backups and delays.

Switching to a night schedule, “we wouldn’t have to deal with the sheer volume of traffic” that transverse Waverley Square with the added benefit that most of the square’s businesses closed for the day, he said.

Saying that he doesn’t like to work after normal hours, “[i]t’s just so congested there that it makes sense to do it at night,” said Barrile.

While the selectmen were supportive of the time change for the repaving, they were not happy with the DOT’s initial proposal to begin the work on Wednesday, July 23, just two days after their meeting.

 

“There are quite a few residences in that area that will be only given a day notice before construction starts and I have a concern with that,” said Selectman Mark Paolillo.

While conceding construction noise will impact residencies, Glenn Clancy, Belmont’s director of the Office of Community Development, said “the tradeoff goes back to 30,000 vehicles trying to get through there during a work day coupled with the fact that businesses trying to operate during the day; the night work seems to be the best alternative to get the job done quickly.”

But Paolillo said the idea of beginning a major construction work through the night and the early morning, “right outside your house” will not give residents the opportunity to make other arrangements.

Selectmen Chair Andy Rojas offered up a Monday start “that gives us time to adequately to notify residents of the nature of the work.” Along with a series of mitigation suggestions – such as positioning construction lighting so it is directed onto the street and a contact number for residents to call the contractor during construction – the selectmen voted to approve the night time work request.

The five day delay will not have much of an impact on the project’s schedule, said Barrile.

“We’ll continue to work on other items such as sidewalks and paving,” he said. “We just want to have that piece of roadway nice and smooth for a change.”

Unchallenged, Belmont’s State Legislators Re-Election Secured Early

It’s a fairly good bet that Belmont residents will be coming out in large numbers for this year’s primary (Sept. 9) and general (Nov. 4) elections. With wide-open contests for most of the big state offices including governor and plenty of ballot questions – a statewide casino ban and paid sick leave – voters should be staying up into the night viewing results.But it will be early evenings for Belmont’s Beacon Hill representatives; while there’s tremendous interest in a wide array of political races on the 2014 ballot, State Sen. Will Brownsberger and State Rep. Dave Rogers find their re-election paths unimpeded by potential challengers for their elected offices.

For Brownsberger – who represents the 2nd Suffolk & Middlesex which includes his Belmont hometown, Watertown and precincts in Boston and Cambridge – after seemingly running continuously for the past several election cycles, “[i]t’s a relief.

“I’ve had a campaign every year in each of the last four years and I welcome the breather,” said won a special election for his current seat in early 2012 but was defeated last year in the race to replace Edward Markey in the US House of Representatives.

For Rogers, who won the seat in a 2012 special election to replace Brownsberger representing the House’s 24th Middlesex, the “ABC” district – comprising precincts in Arlington, Belmont and parts of Rogers’ hometown of Cambridge – while he enjoys campaigning, there is the downside of gladhanding with residents.

“It is a highly time-intensive activity that inevitably would distract any incumbent candidate from the substantive aspects of the job.”

While seemingly minor open races – such as for Lt. Governor – have people willing to throw their hats into those rings, potential challengers to Brownsberger and Rogers would be required to take on an incumbent who have solid support in their districts for their steady, if workaday, legislative records.

“It is hard to say why I do not have an opponent without getting into random speculation,” said Rogers.

“But I hope that, in part, it is a reflection of the considerable effort I am putting forth on behalf of the people I represent, effort that has yielded a number of important, positive developments for our community,” said Rogers, who points to boosting public transportation and public education funding, increasing the minimum wage to the highest in the nation as recent accomplishments.

“Hopefully, people feel I’m doing a good job,” suggested Brownsberger.

In addition, the legislators have the ability to raise the cash needed to run a primary campaign. I probably didn’t go unnoticed by anyone with political ambitions in the “ABC” district that popular Massachusetts Gov. Deval Patrick would come straight from Logan to highlight Rogers’ fundraiser earlier in the year.

With re-election all but certain, Brownsberger and Rogers are gearing up for the next legislative year in advance of the election of a new governor.

“I’m getting more done than ever before,” said Brownsberger, who was recently appointed by Senate leadership to co-chair the prominent Judiciary Joint Committee.

“I feel I’m hitting my stride and taking on a lot of responsibility in the legislature. I am delivering a lot of value for my district and the Commonwealth,” he said.

“When Patrick came to Belmont in April to endorse me at my re-election campaign kickoff, he told a large, enthusiastic crowd that I had shown political courage on Beacon Hill. I had championed the values and voted for the public policy goals about which my constituents care, even when at times under fairly intense pressure to vote a different way,” said Rogers.

“I believe that I have hit the ground running, and I look forward to continuing service to the community. It’s very hard work, but it’s also a great honor, deeply rewarding and a lot of fun,” he said.

Helping Repair A Place in Belmont History

Nineteen-year-old Army Private James Paul White – known by his friends as “Whitey” – had seen his share of war in just the month he spent on the front lines in 1944.

White – a member of Co. G, 26th Infantry Regiment, 1st Infantry Division, “The Big Red One,” – had fought as part of the US Army’s advance into the Huertgen Forest, “a miserable and treacherous affair” that lasted until the first week of December, recalled White’s unit commander, 1st Lt. August T. ‘Mac’ McColgan, in 2004.

It must have been a hard time for the replacement to a battle-hardened company

“All of the battles in the past were just rehearsals for what was yet to come” on Dec. 16, said McColgan, when some 24 German divisions, 10 of them armored, launched a massive counterattack in the Ardennes region of Belgium that began what was to be called the Battle of the Bulge. The 26th, known as the “Blue Spaders,” would fight on the northern edge of the enemy’s advance, near the small Belgium hamlet of Don Bütgenbach.

“The Battalion Commander finished his attack order with the statement, ‘Gentlemen we fight and die here.’ Many did die there, friend and foe alike,” wrote McColgan in 2000.

We established our defensive position astride the Bütgenbach/Büllingen Road. We, G Co., 26th Infantry established the “Hot Corner,” said McColgan in his war memoir, “The Battle of the Bulge – Part III – Hell at Bütgenbach.”

On Dec. 20, White – who was a veteran member of the outstanding 1942 baseball team of Belmont High School where he graduated in 1943 – would face with his fellow soldiers the might of the German Wehrmacht. Enemy tanks launched an attack on their position on “a dark, damp and foreboding morning,” many which succeeding in penetrating parts of the US line. Only through close-range combat was the attack propelled back.

Following a night and early morning which White and his comrades were subjected to an artillery barrage that was “by far the worse the defenders of Dom Bütgenbach had experience in the whole war,” a final all-out push with an ever greater armored force began at dawn on a foggy Thursday, Dec. 21.

Once again, the 26th successfully beat back the enemy’s attack in which infantry drove back the Germans. For his actions during that battle, the 26th’s Cpl. Henry Warner would be awarded the Medal of Honor posthumous.  

And in the snow and bitter cold of a field in Belgium on the day before winter, White laid dead, one of 19,000 Americans killed in the 10-day battle.

In May 1948, a year after White’s body was sent from Europe for burial in the US, Belmont honored White by naming the athletic field house on Concord Avenue for him.

A bronze plaque reads that White was “[a]n athlete trained on the Belmont playgrounds” who was “representative of the youth of Belmont who served their country in World War II.”

“Freedom lives and through it he lives.”

The memorial, which hangs just inside the front door of the 82-year-old structure, is more than simply an aging tablet to the long dead. It became one of the reasons inspiring Woodfall Road resident Frederick Jones to move towards “refurbishing” the interior of Belmont High School’s athletic facility used by numerous teams which play on Harris Field or the Viglirolo Skating Rink during the school year.

“The plaque is quite moving,” Jones told the Belmontonian before attending the Belmont School Committee’s meeting on Tuesday, June 24. “It’s well worth reading by every resident.”

Jones said the structure is a state-recognized historic building – that is owned by the School District – that “we all drive by every day on Concord Avenue which also has an interesting architectural history.”

“But it’s also a historic memorial for a town figure. It makes you feel that there should be something better to continue this memorial to this hero and to all veterans,” said Jones, whose son plays football and was a finalist in the 200 meter dash in the All-State meet earlier this month.

Yet for anyone who has entered the field house can observe, the interior – which has four locker rooms – hasn’t changed much since the day it was renamed more than 65 years ago. The lockers are circa 1940s, “old, battered and far too small and narrow for modern equipment,” said Jones, forcing hockey and football players to leave large bags and personal items on the floor or on top of the lockers. The paint is old, the emergency lights don’t work and the communal showers harken back to the YMCAs of a bygone age.

“It is quite remarkable the conditions inside the field house,” Jones lamented.

“We know how hard the athletes work … and it seems right to give them a better facility,” said Jones.

Yet years of delayed maintenance has taken its toll on the structure as capital spending is limited and greater priorities for the Capital Budget Committee arise on an annual basis.

Knowing the challenges facing any facility needing long-term funding in Belmont, “our idea was to step in and do some simple things that will refresh it,” said Jones.

The result of many brainstorming sessions by Jones and a core committee he set up resulted in raising nearly $40,000 in outside pledges of the $50,000 they are seeking to raise along with contacting contractors who can do the job.

The project is divided into several “discrete modules” that were ranked in order of importance with the lockers being the most pressing need. Next will be replacing the electrical system and updating the lighting fixtures and emergency lighting system, performing a top-to-bottom cleaning, repaint the inside and then place partitions in the showers for privacy.

And work is currently underway inside the field house with material begin stacked up in the ground floor entry way.

Jones and his group will be working with the town’s Facilities Manager, Gerry Boyle, and the school’s Athletic Director James Davis as well as the Brendan Grant Foundation which will allow anyone donating to the effort to receive a tax deduction for their contribution.

“The support we have receive has been very encouraging and has helped our fundraising,” said Jones.

Yet what this one group of parents and supporters has done is expose the inability of the town to sufficiently fund what is required from either the school or capital budgets, said the School Committee’s Kevin Cunningham.

“I’m not sure what the moral of that is except that an additional amount of effort is not coming from the core fund but from volunteers and donations,” said Cunningham.

 

Belmont Schools, Teachers Union Sign Three-Year Deal

Limitations to Belmont’s financial future and job security trumped demands for big pay increases as the Belmont School Committee and Andy Rojas, chair of the Belmont Board of Selectmen, approved three-year labor agreements with the four bargaining units represented by the Belmont Education Association on Tuesday, June 24.

“There’s been a relationship of honest communication and trust established that we can build upon,” BEA President John Sullivan told the Belmontonian after the committee’s regularly scheduled meeting held at the Chenery Middle School.

“We hope that the process producing these agreements has helped deepen relationships based on trust and mutual understanding that will support teaching and learning through the life of these contracts,” said a press release dated Wednesday, June 25 that was signed by Belmont School Committee chair Laurie Slap and Sullivan.

After a year-long negotiation, the union and the committee reached the tentative agreements on Thursday, June 12 with the BEA units approving the four respective agreements on Wednesday, June 18.

The four units comprise teachers (Unit A), directors and assistant principals (Unit B), clerical employees (Unit C) and paraprofessionals (Unit D).

On the salary front for teachers – that makes up the largest BEA unit with approximately 300 members – most of the increases over the next three years will be going to the most senior of the teachers. Those with 14 or more years of service, known as “top spots,” will receive the bulk of increase:

  • Year one, only the “top” educators will receive a 1 percent increase,
  • Year two a 2 percent increase for the top educators while those with 13 years or less will receive a 1 percent increase, and
  • Year three, top step educators will get a 2.5 percent with the less-senior educators receiving 1 percent again.

Yet those increases have been tampered down by the effective dates of the jump in salaries; increases in the first year will not begin showing up in pay packages until the 113th day of the year, with similar delays in the subsequent years; 109 days in year two and 121 days in year three.

“So the one percent increase in the first year is really about 80 cents to the dollar,” said Sullivan, a teacher at Belmont High School who led the union’s 10-member negotiating team.

“We believe the compensation picture has stayed within the projected available revenue that will be coming to the school department over the next three fiscal years,” said Belmont District Superintendent Dr. Thomas Kingston who participated in his final committee meeting before department from his three year “interim” position on June 30.

While the contract’s pay compensation increase is sparse for most teachers – two percent over two years – the membership approved the union’s package overwhelmingly, said Sullivan.

“We had a lot of questions on salaries in our meeting last week,” said Sullivan, having met with his membership for an hour before the votes was taken last week.

Modest increase in salary

“There was faith in the team and trusted the work that we had done with the school committee. … [the] compensation package allows Belmont to say competitive in retain and attract highly-qualified teachers,” said Sullivan.

In a recent Boston Business Journal report, Belmont teachers ranked 30th in state according to salary information from 2011 with an average teacher’s salary of just lower than $80,000.

“We remain on that upper level of compensation with other towns so we are competitive,” said Sullivan.

The relatively modest pay increases for Belmont teachers in this contract is based on the acceptance by both sides that the town is unlikely to see any appreciable increase in available revenue for the foreseeable future.

The realization Belmont relies heavily on residential property taxes – whose increases are limited to 2 1/2 percent annually – while lacking the capacity to generate tax revenue from new growth such as commercial real estate or fees restricted what the union could ask for and the town to give.

“The agreements provide for compensation in line with projected annual School Department revenues for fiscal years 2015, 2016, and 2017,” said the School Committee press release.

Both the committee and Sullivan said the most important issue facing the sides was that the district “remains committed to attract and retain a highly qualified staff that meets the needs of our students,” according the committee’s press release.

The other major agreement achieved in the contract is job protection for paraprofessional such as teacher’s aides. The new contract states that at the end of the 2015-16 school year, no [paraprofessional] who has successfully completed five years of service can only be dismissed with “good cause.” In addition, a new evaluation system will be jointly negotiated during the upcoming school year.

“We have a highly-dedicated group of professional aides that does a great job supporting students. It’s a sign of respect and [they] feel better with their position within the district,” said Sullivan.

In addition to the job protections for the aides, the agreements also provides the standardization of clerical personnel job classifications and pay-for-performance benefits to directors and assistant principals, said the press release.

The agreement continues the “step and lane” salary schedule in which teachers receive pay for years of service and education level they achieve.

Kingston said while he continues to believe “step and lane” compensation is “unsustainable,” he said this contracts mitigates the formula by acknowledging the limits on revenue growth.

Both sides agreed that employing in part the principles of interest-based bargaining – in which both sides expressed their underlying interests for each request – greatly assisted the negotiation process.

The committee and the town will also be created a Joint Labor-Management Committee to “continue addressing district-wide issues of mutual concern,” said the press release.

“It’s building on the relationships we’ve established so we won’t have as many items in three years with the next contract,” said Sullivan.

“We don’t want to put everything on hold for three years,” said Slap.

The specific details of the agreements are available on the Belmont School Department’s website under the School Committee tab in the next few days.

School Committee, Teachers Set to Sign Three-Year Contract Tuesday

After nearly a year of weekly negotiations and late-night meetings, the Belmont School Committee and the Belmont Education Association, the agent for Belmont’s classroom instructors, will sign a new three-year memoranda of agreement at the committee’s regularly scheduled meeting on Tuesday, June 24.

The contact will be signed by BEA President John Sullivan. The BEA represents the district’s school teachers, assistant principals, coordinators, teacher aides/instructional support staff and campus monitors.

Sources contacted by the Belmontonian would not go into detail on the specifics in the contract including the percentage salary increase or whether the two sides have agreed to continue the “steps and lanes” salary schedule. Steps refer to how many years a teacher has been teaching, and lanes refer to how much education the teacher has.

Under the current three-year contract, set to expire on Aug. 31, first year teacher with a bachelor’s degree received $46,546 in fiscal year 2014 while a first year educator with a PhD would earn $55,788. At the top end, a PhD with 15 years of work experience makes just under $100,000.

Belmont School Superintendent Dr. Thomas Kingston – who is leaving his position on June 30 – has been publicly critical of the steps and lanes schedules as pay increases are automatically given to educators without consideration for performance. Other critics contend an across-the-board pay increase would be a fair substitute of the current structure.

Supporters of the current pay schedule say that it provides transparency as they are based on easily quantifiable measures ensuring equitable salaries without biases towards teachers and allows those educators to plan for the future by giving them a reasonable assurance of their yearly income.

Zoning Board Tells Developer to Finalize Starbucks Move Before Returning

Eric Smith had enough.

The Zoning Board of Appeals member had been unhappily listening to the representatives of Cushing Village – the proposed 186,000 square foot, three building residential/retail/parking complex in the heart of Cushing Square – who is seeking to temporarily relocate the popular Starbucks Coffee Cafe at 112 Trapelo Rd. up the street while the development is being built.

He, his fellow board members and about 40 residents who filled the Belmont Gallery of Art in the Homer Building Monday night, June 16, were hearing from Development Consultant Gerry Pucillo, representing Cushing Village developer Chris Starr’s Smith Legacy Partners, discussing a last minute agreement with Belmont officials to construct temporary parking spaces – how many remains a matter of dispute – on the traffic island across from Moozy’s Ice Cream in an attempt to resolve concerns of parking and traffic many in the nearby residential neighborhoods have with Starbucks coming to the new location across from Trapelo Road and Pine Street.

(Smith Legacy Partners is representing Starbucks before the ZBA in requesting a pair of special permits at 6-8 Trapelo Rd., the first to retrofit the facade and window and the second is to operate a restaurant in a non-conforming zoning location.

But as Pucillo and Cushing Village architect Peter Quinn discussed the proposed parking solution which was “agreed to” earlier in the day with Belmont’s Town Engineer Glenn Clancy, it became apparent to White that the board’s request to the development team at the May public meeting to return with solutions that could be discussed and voted on would not be forthcoming at Monday’s June meeting.

“From what I was hearing, we were going to spend a lot of time and end up going nowhere again,” said Smith to the Belmontonian after the meeting.

About 25 minutes into the discussion, Smith spoke up, suggested to ZBA Chairman William Chin that despite what was being said, Pucillo was not presenting “an actual parking proposal in front of us right now” nor was he addressing Board of Health  concerns on placing a second dumpster in the area.

“We have spent a lot of time this evening hearing a lot of comments but it seems to me that we don’t have a concrete enough plan to act upon,” said Smith, asking that Smith Legacy return once again to the ZBA at which time they can finally resolve the ongoing concerns from neighbors and town boards and officials of the propose move.

It was a decision that Chin wasted little time in agreeing to, asking that, once again, a parking plan be developed, the issue with trash collection, deliveries

What was learned during Monday’s meeting was:

IMG_1264

• A proposed parking solution agreed to between Smith Legacy and the Office of Community Development would create a limited number of angled parking spaces – the developer is claiming they only need six spaces to meet zoning requirements while the ZBA believes the number closer to eight – in the town-owned traffic “island” that borders the entry to Watertown’s Oakley Country Club and is across from Moozy’s. No trees will be harmed in the construction of the spaces – which would be on the Oakley side of the island – according to Pucillo, and the spaces would be removed after Starbucks is relocated.

But as a town official noted to the Belmontonian, while Community Development can suggest this solution, it would ultimately be up to the Belmont Board of Selectmen whether to approve the use of town-owned land for this proposal.

• Once Starbucks returns to its new “home” in Cushing Village, the site will “revert back to retail spaces” and not remain a site for a new restaurant or cafe, said Pucillo.

• Starbucks employees will be reserved five parking spaces at the VFW lot, at 310 Trapelo Rd., across from the Belmont Fire Department headquarters and take the MBTA’s Route 73 bus to the relocated site.

• Pucillo said that construction on Cushing Village will begin in October, the same month Starbucks “must relocate at the latest.”

While residents did get to speak on many of the same issues they expressed a month before, Oak Avenue’s Rickland Powell and David Alper both asked if Starbucks will benefit from the special permits, that it should come before the residents to “give concrete answers” to their questions, said Alper. 

Starbucks Temporary Relocation On Zoning Board Agenda Tonight

The Belmont Zoning Board of Appeals tonight, Monday, June 16 will reconvene its hearing from last month on the temporary relocation of the Cushing Square Starbucks Coffee Cafe to the intersection of Belmont Street and Trapelo Road, a meeting that brought out nearly 40 residents voicing concern on the possible increase in traffic and parking as well as questioned trash migrating into the abutting neighborhoods.

The meeting will take place at 7 p.m. in the Belmont Gallery of Art, on the third floor of the Homer Building, located in the Town Hall complex in Belmont Center.

The original meeting, held on Monday, May 19, brought out residents who heard the popular Cushing Square Starbucks would temporarily move for about a year from its present location at 112 Trapelo Road up the road to 6-8 Trapelo which is less than a block from the intersection of Belmont and Pine streets. 

The move is necessary due to the construction of Cushing Village, the 186,000 sq.-ft. multi-building residential/retail/parking complex being constructed by developer Chris Starr of Smith Legacy Partners. Starr’s company also owns the two storefronts which the cafe would move into.

Smith Legacy is seeking a pair of special permits for the relocation; one to performs renovations to the exterior and the second to run a restaurant at the site.

Residents of the nearby neighborhoods told the board at last month’s meeting of their worries that the cafe, with nearly 50 seats, will aggrandize parking problems facing the adjacent residential streets that are currently being used by commuters. They also voiced worries of greater trash and litter in their community and other nuisances.

Belmont High’s Harris Field Closed Until August

Belmont High School’s Harris Field and its running track at the Concord Avenue Athletic Complex, a favorite destination in Belmont for youth teams, runners and for pickup games, are now officially “closed” for long-anticipated renovations beginning today, Monday, June 16, according to Judi Carmody, business manager of the Belmont Department of Public Works. 

The work is expected to last until Aug. 15, a week before the beginning of practice for the fall High School sports season. 

The $960,000 job, in which the synthetic turf “carpet” will be replaced, fencing and walkways repaired and the track resurfaced and relined, was authorized by the special Town Meeting in November 2013. The funding is coming from an extension of bonding that paid for the uni-vents at the High School. 

“We regret any inconvenience that these improvements may cause,” said Carmody. Residents who have any questions can call the DPW at 617-993-2680 or email at BelmontDPW@belmont-ma.gov

A November Override Vote Now ‘Nil’ Due to State, Town Deadlines

The hope of advocates for Belmont schools and town services to place a multi-year operational Proposition 2 1/2 override on the November ballot has been quashed by a combination of a tight state deadline and insufficient time for a committee reviewing the towns financial health to complete its work in time, according to the Selectmen’s chair.

According to Brian McNiff, spokesperson of the Massachusetts Secretary of State office, the secretary’s deadline for reviewing and approving the Proposition 2 1/2 override language so it can be placed on the November 4 state election ballot is August 6.

“[The town] has to have all the work done by that date so we can do the legal review required,” said McNiff.

Andy Rojas, chair of the Belmont Board of Selectmen – the municipal body under state law that must approve both the language and determine whether the town requires an override – told the Belmontonian Wednesday, June 11, a summer cutoff point from the state on top of notification requirements on the Town Clerk all but dooms the proposed November override ballot question.

The early August state drop dead date will not allow the Financial Task Force, a 13-member “mega” committee created last year to conduct a comprehensive review of the town’s finances, highlight possible revenue streams and develop a long-range financial and capital improvement plan, any chance of completing the analysis the Selectmen would require.

“The chances that the Financial Task Force … finishing any of its work to the point where we can reach any clarity on an override is now apparently nil,” said Rojas.

Municipalities must follow a precise list of procedures mandated by the state Secretary of State and the Department of Revenue to place an override question on the ballot.

“It is a very strict on what we require from the towns,” said McNiff, as municipalities follow a template on the why, how much and when of an override request.

Under state law, a Proposition 21⁄2 referenda questions can be placed on the state biennial – every two years – election ballot which has become an important point by Belmont override advocates who hope to benefit from strong voter turnout in a November election with state-wide races – including what many predict will be a competitive race for governor – on the ballot.

“However, those questions must be submitted to the Secretary of State for certification by the first Wednesday in August preceding the [biennial] election. G.L. c. 59, § 21C(i),” according to language on the Revenue Department’s web site. (http://www.mass.gov/dor/docs/dls/publ/misc/prop2.pdf)

In addition to state requirements, Belmont’s Town Clerk “must receive written notice of the referendum at least 35 days before the date of the election. The vote to place a question on the ballot must take place in sufficient time to meet this advance notice requirement,” reads the regulations.

While the Task Force has been working since the beginning of the year on the town’s finances, “they are still working through the facts,” said Rojas.

Rojas said he continues to support placing an override on the ballot “once we have all the information” to determine the need to permanently raise the tax levy.

“I think … the earliest voters will have a chance to vote on the override will be the [annual] Town Election in April,” said Rojas.

Get In Line: Community Preservation Set Dates for Applying for Funding

Do you have a project that could use a few dollars to complete?

Well, you may want to get in line to apply for what will be the third funding round from the town’s Community Preservation Committee which distributes the total of a 1.5 percent surcharge on property taxes and state funding for a wide-range of proposals involving acquiring or improving open space and recreation land, rehabbing or preserving historic sites and supporting community housing.

Preliminary applications for CPC funds will be available on July 1 from the committee. But already “eight or nine” groups have made inquires on the process, according to Floyd Carman, Belmont’s treasurer and committee’s clerk.

“Residents have seen the process work and now are thinking about it for their proposals,” said Carman.

And the committee will be holding a tidy amount of cash to help jump start projects.

At its monthly committee on Wednesday, June 11, the CPC estimates it will have a little more than $1.1 million to distribute to organizations or town agencies in the 2016 fiscal year beginning July 1, 2015, said Michael Trainor, the CPC coordinator.

That total could increase with the approval of an additional $25 million in additional state matching funds distributed across the state that could up Belmont’s total to $1.4 million, said Trainor.

But groups which believe simply by applying for CPC funding guarantees the money in their bank account will benefit attending the public meeting on Sept. 18 where the committee will answer questions and review the extensive process in which projects are evaluated.

Preliminary applications are due in on Sept. 30. A week later, on Oct. 8, the committee will make the first round of cuts. Groups whose proposals past muster will make a five-minute presentations and answer questions from the committee on Nov. 13. Final applications are due on Dec. 1.

The CPC will make its final decision on accepting or rejecting applications on Jan. 14, 2015.

In April, the CPC made its largest distribution by providing $2 million for the new Underwood Pool. But the committee usually allocates smaller amounts to such projects as $165,000 for the electrical upgrade of town housing, $8,700 to improve the irrigation system at the High School’s “JV” field and $67,000 for the second phase of the Butler School Playground project.

This fiscal year, Carman is advising the committee to create a “reserve” account, setting aside a specific amount annually to build up a funding source to use on acquisitions or projects exceeding the entire funding amount in any future year.

For more information, contact the Community Preservation Hotline at 617-993-2774 or Trainor at mtrainor@belmont-ma.gov