Photo: The work is underway at the newly dubbed Bradford in Cushing Square.
The Starbucks Cafe has closed and the Trapelo Raod is about to be dug up as the developer of the Cushing Vill … The Bradford prepares to move forward with excuvation and infrastructure work at the 167,000 sq.-ft. residential/retail/parking complex.
Otto Weiss, project manager for Toll Brothers Apartment Living who is building the development told the Belmontonian on Tuesday, June 7, construction is “on schedule” and, weather permitting, the foundation for the Winslow – the first of three buildings on the site located at the former municipal parking lot adjacent Trapelo Road – will be poured in early August.
He also said the company will officially take possession of the now closed Starbuck’s cafe on Monday, June 12 and the building – which was constructed as a Friendly’s restaurant in the 1970s – will be razed starting on Wednesday, June 14.
In preparation to the demolision, “[o]n Monday (June 12) we will relocate site fencing that runs behind Starbucks to the curb at Trapelo Road and tie it into the fence running from the corner of Common Street,” said Weiss in a press release sent on Friday, June 9.
The side walk between Williston and Common Street along Trapelo road on the project side will be close to pedestrian traffic and signage will be installed instructing pedestrians to cross the street at Williston Road and Common Street.
All utility cut offs will be performed on Monday, June 12, weather permitting, which will require utility crews with trucks working in the street. Police details will start at 7 a.m. on Monday.
The utility shut-offs should not affect service to the surrounding community, said Weiss.
“However the various utility companies may inform you of shut offs need to accommodate their work. That would be out of our control. If we are notified of any suck shut offs we will pass the information along immediately,” he said.