Photo: A big purple hole in the ground.
As the digging on the future home of Cushing Vill … sorry, The Bradford is speeding along on schedule, more than one resident who spied into what will become the foundations of the three buildings making up the 164,000 sq.-ft. complex of apartments, stores, and parking in Cushing Square was taken aback by the rather strange purplish hue to the ground water and soil in the pit.
Did the contractor Nauset Construction find something no one was expecting to discover?
One person who did take notice was the Otto Weiss, the project manager for Toll Brothers Apartment Living, the Bradford’s owner/developer.
“[Y]ou may notice that the color of the treated soil and any surrounding water is clearly purple,” said Otto Weiss, the project manager for Toll Brothers Apartment Living, the Bradford’s owner/developer.
What nearby neighbors had noticed was just what the team was expecting to find.
“This is a normal reaction of the treatment process and is not a cause for alarm,” noted Weiss in an email project update.
“I realize you may have questions and as always I will do my best to answer,” said Weiss, who can be contacted at oweiss@tollbrothers.com
Weiss said the treatment process that was approved earlier this year by the Massachusetts Department of Environmental Protection will take about one more week to complete, at which time the site will undergo several weeks of testing and approvals before the removal of the soil.
Ongoing air testing and monitoring continues uninterrupted, “and to date we have not seen any results that cause concern,” said Weiss.
The signs the popular Starbucks cafe, located on Trapelo Road in the middle of the active construction site, is winding down operations is literally on its doors. A pair of notices referred customers to big changes to the hours of operations – the store will close at 5 p.m. starting May 22 and at noon a week later on May 29 – and a “thank you” note to customers are located at both entrances and inside the not so busy store.
“Thank you for your patience and understanding as we prepare for this store to close,” said Store Manager Matthew Thompson.
No closing date has been provided. Toll Brothers said a new Starbucks will be opening in the early fall of 2018 in the “Winslow” building which is located on the former municipal parking lot.