Road Construction On Four Streets Begins April 10; Work Complete In Two Weeks

Photo: Van Ness Road will be one of four streets in Belmont to undergo road construction beginning April 10.

Weather permitting, on Monday, April 10, the Town of Belmont’s general contractor, Newport Construction, will begin full-depth road construction on Amelia Street and Becket, Clairmont, and Van Ness roads, according to a press release from Town Engineer Glen Clancy.

These roads will be closed to all traffic between 6:30 a.m. and 6 p.m. This work is expected to be completed in two weeks.

This phase will include removing the manhole covers and water grates. Pulverizing the road, grading, and finally placing the first layer of asphalt will then occur.

Residents and commuters are advised to seek alternate routes. No on-street parking will be available, and access to driveways will be limited during construction hours. Residents affected by the construction can park overnight on nearby side streets.

For any questions or concerns about the project, don’t hesitate to contact the Office of Community Development at 617-993-2665.

Snow Emergency Lifted at Noon, Monday; Remember To Clear Your Walk

Photo: Now comes the shoveling

The Belmont Snow Emergency Parking Ban was lifted effective noon, Monday, March 4.

Below is a reminder from Belmont’s Office of Community Development:

“The town’s residential snow removal bylaw requires sidewalks along residential property to be cleared of snow and ice by 8 p.m. the day after a storm ends. With regards to today’s storm, snow and ice should be cleared or treated from sidewalks to a width of at least 36 inches by 8 p.m., Tuesday, March 5.”

“We appreciate your attention to this very important public safety matter. Please refer to the Town’s web site for further information regarding winter weather and the Town’s snow removal bylaw.”

https://www.belmont-ma.gov/sites/belmontma/files/news/residential_snow_removal_bylaw_information.pdf

https://www.belmont-ma.gov/sites/belmontma/files/uploads/60-800_i.pdf

If you have any questions, contact the Town of Belmont’s Office of Community Development at 617-993-2650 during normal business hours.

A Labor Lockout Could Keep Belmont Streets Unpaved ‘Til Spring

Photo: Common Street.

The money is in the bank, the contractors are ready to go and long-suffering residents are waiting with bated breath.

But for homeowners along four Belmont roadways, a labor dispute between workers and an international utility firm is threatening to delay the reconstruction and repaving their streets until this coming Spring.

The prediction by Town Engineer Glen Clancy to the Board of Selectmen at its Monday night meeting, Aug. 20, relates to a month-long lockout of 1,100 union gas workers by employer National Grid after the two sides could not reach an agreement on a new longer-term contract in June.

Now Belmont residents are locked out of a promised a new road after suffering through detours and delays for the past year.

“I just want the community to understand that … the town and DPW (Department of Public Works) are obviously aware of the conditions of these roads,” said Clancy.

In each case, permitted infrastructure projects – such as the installation of gas lines – are uncompleted. Under current town policy, the Office of Community Development will not release funds for roadways that require expensive gas, water, and electrical work in the near future even if it was approved by Town Meeting.

“With National Grid being locked out, the utility work necessary to finish those projects are at a standstill,” said Clancy.

Clancy said many complaints relating to the condition of Common Street which runs from just outside Belmont Center to Cushing Square and to the Watertown line. 

Other streets include Payson Road, Lawndale and Prospect streets which were selected in the past year to be part of the annual pavement management program which sets aside funds to reconstruct streets the town determines to be in the most need of repair.

“I want people to understand that if not for the lockout, it’s likely that Clifton and Prospect streets would be finished since most of the major work is complete,” said Clancy, noting that Common Street is under the 2017 pavement management contract, “so all we are waiting for is for the street to be fixed.” 

While the beginning of winter – and the end of the reconstruction and paving season – is not yet around the corner, Clancy said unless the lockout is resolved soon, DPW will need to consider a stop-gap solution “to make sure those roads are safe for driving until the spring of 2019.” He pointed to the temporary top coat of asphalt placed on Grove Street last winter as an example. 

“[National Grid] has been put on notice for that job,” said Clancy.

Answering a question from Selectman Tom Caputo, Clancy said mid-September would the latest date to begin reconstruction and replacement for any street, providing six good weeks before the weather conditions turn “sketchy.” 

“We have a little bit of time but the clock is ticking,” said Caputo. Worst case scenario, according to Clancy, is the work will be scheduled to begin in eight to nine months from Sept. 1. But even if the lockout is resolved in the next few weeks, there is no guarantee National Grid would be able to send the necessary crews to finish the work as the firm is currently backlogged with jobs.

The one “good” result of the management action is it now allows the lining of the large MWRA water main along nearly the length of Common Street to be completed without competing with National Grid crews, said Clancy. 

Correction: The labor action between National Grid and the unionized workers is a lockout, not a strike.

Are You One Of The Lucky 13? Town Selects Baker’s Dozen For Street Repair In 2019

Photo:

A lucky 13 town streets will undergo renovation and repave a year from now in 2019 as the Office of Community Development released the annual list of roads to be reconstructed under the Pavement Management Program. The streets are selected through a set of criteria that includes the condition of the road and it all infrastructure work has been completed.

The streets that will see repairs begun in the spring of next year include:

  • Alma Avenue (from Bartlett to Belmont)
  • Newton Street (Belmont to Fairview)
  • Ridge Road (Belmont to White)
  • Juniper Road (Somerset to Fletcher)
  • Carleton Road (Washington to Chester)
  • Harriet Avenue (Bartlett to Belmont)
  • Indian Hill Road (Old Middlesex to Oakley)
  • Essex Road (Benton to Old Middlesex)
  • Preble Gardens Road (Old Middlesex to Oakley)
  • Old Middlesex Road (Oakley to Benton)
  • Benton Road (Payson to Oakley)
  • Townsend Road (Payson N to Payson S)
  • Alexander Avenue (Leonard to Claflin)