While Middle And High School (Nearly) On Budget, COVID Looms Over Project

Photo:

At its 99th meeting since it first met in 2016, the Belmont Middle and High School Building Committee on Wednesday, May 13 inched closer to realizing a milestone in the construction of the 451,575 sq.-ft. project as it closes in on finalizing the project’s Guaranteed Maximum Price.

With all the actual bids received by the general contractor, Skanska, and through the oversight of the project by the board (which included a series of value engineering exercises earlier in the process by the building committee to balance the preliminary budgets) the project is at the point where the committee can compare this actual cost of the project against the initial estimated price tag.

The final price of the project is comprised of the bids received, the amount of contingency used, and agreed upon general conditions/fee. Under the GMP, Skanska is compensated for all actual costs incurred from the first day of construction – actually some costs before then – onward.

Going forward, Skanska is responsible for all cost overruns, unless the GMP is increased via formal “change orders” that alters the scope of the project. To reduce their risk and cover any unforeseen costs, Skanska has a contingency fee built into the budget.

And the GMP is darn close to the original price tag for the project. Initially pegged at $238,619,850 – this figure has been revised slightly upwards with allowed transfers of preconstruction costs – after all the steel, cement, rebar wire and thousands of other material and services have been cited and reviewed, the project’s GMP has come in at $240,041,815.

And while the discrepancy results in an overage of $1,421,335, Building Committee Chair William Lovallo told the committee having the GMP coming within a half of a percent of the original estimate on a project this large was commendable.

“I think we did a darn good job,” he said, although admitting $1.4 million “is still a big number.”

Three options facing the committee

While the committee member will be digesting the facts and figures over the weekend – a final approval will come at Wednesday’s May 20 virtual meeting – Lovallo said the once the committee OKs the $240.0 million GMP, it has three options to reconcile the deficit:

  • Approve the GMP and resolve the deficit using the contractor’s contingency fund, currently at $16 million.
  • Ask Skanska to find a way to come up with $1.4 million in cost savings, and
  • Enter into a third round of value engineering that requires reopening the expenses column and cutting items that are ready to be added to the building.

While there was some give and take among building committee members on what could be crossed out at this late time – the most focus was on the artificial turf “rugby” field at $700,000, it became apparent that most members were not amiable to revisiting the process.

“We have gone painstakingly through the [value engineering] process and … determined what we placed high value on and made decisions about it,” said Steve Dorrance, the town’s director of facilities, who asked that a straw poll on members preference be taken. It soon became evident the committee members clearly favored using the contingency account and be done with it.

Lovallo told the members they “shouldn’t beat itself up” if it decided to go the contingency route as the contractor and committee have been frugal using the account.

But despite the silver lining around the GMP process, the dark cloud of the coronavirus pandemic has the potential of floating over the project. While the project still has a “substantial amount of money left” in its contingency funds – totaling roughly $18.5 million if you include the owners account and other smaller line items – Lovallo said that money could be seen as quite small if COVID-19 makes a substantial return in the fall or winter.

In a worse case scenario of a major resurgence that forces the closure of the building site or reduce the number of workers on the site to 25 would likely result in millions in incremental costs to the project. Lovallo said that similar sized projects in the Boston area have experienced losses in “seven figures.”

At that point, Belmont would have to really reconsider the project. I don’t see how [the town] would want to be supporting 10s of millions of dollars in COVID costs. It just doesn’t make any sense,” said Lovallo.

“There’s a big discussion we have to have and understand what the options ared of maybe shutting a job down and starting up when work can be a lot more efficient than just pumping millions of dollars into it … just to keep it going.”

‘Virtual’ Topping Off At Middle/High School Project Set For Late April

Photo: Pouring cement onto the second floor of Area B.

Over the course of the past month, the coronavirus has forced many familiar activities to become virtual events via the internet including working from home, attending town meetings and school.

Now you can add to that list the traditional construction milestone of “topping off” the new Middle and High School project at Belmont High School set for the final week in April “or the first week in May, at the latest,” according to Mike Morrison, project manager for Skanska USA, as he spoke to the Middle and High School Building Committee on Thursday, April 9.

In pre-pandemic times, members of the construction team, the building committee overseeing the development and town officials would come together to celebrate the final steel beam being hoist into place. Everyone would sign their name to the beam while a small pine tree and Old Glory would be attached to the beam, reminiscent of an old fashion, barn-raising.

So keeping with the new realities, the topping off of the high school section and administration wings of the $295 million project will be done remotely, broadcasted to the community via the internet and on local cable.

But for those who will miss the hoopla, Belmont Superintendent John Phelan pointed out there will be a second topping off, this one for the project’s Middle School section in two to three years down the road.

Morrison took the time to revealed an extensive social distancing plan currently underway at the site due to the ongoing pandemic. Belmont continues to allow the building trades to work on the job where Boston and Cambridge have halted all construction activity due to the novel coronavirus.

“The thing that is on the front of everybody’s mind is COVID-19 and Skanska has taken to heart everything that has come through the CDC, the World Health [Organization] but also from [Gov. Charlie Baker’s] health and safety guidelines,” said Morrison.

In pursuit of keeping its subcontractors healthy, the firm has custom-built foot-controlled handwashing stations with hot and cold water that are more than six feet apart “where they can really clean up” when they arrive, before and after breaks and at the end of the day, said Morrison.

“We’re emphasizing and stressing the physical distancing. … which is still a difficult thing to adapt to” for many longtime construction workers, said Morrison. Skanska has filled the site with signs on keeping a safe distance and proper cleaning as well as instituting a 7 a.m. start of the day camaraderie building session that consists of stretching and flexing and announcements on the latest COVID-19 announcements.

Morrison provided a rundown of the construction highlights in the past month including the pouring of the first concrete slab with radiant heating tubing on the second story of “area B” which is the wing pushing out towards Harris Field. Steelwork in “area A” – the administration wing that juts out towards Concord Avenue – will for all intents and purposes be substantially completed” this week.

He also heralded “the huge accomplishment” of installing a massive 32-ton, 100-foot long steel truss that will support the interior bridge in Area C and D in the high school section.

One section of the job that committees have raised concerns is the installation of the infrastructure for the geothermal system. The drilling expenses in the first of three fields spiked recently adding $275,000 to the project cost in additional water management expenses which included added labor, material, and equipment.

“We’ve had some challenges” with drilling pipes “into the unknown of the underground,” said Morrison, who told the meeting that “we feel like we have enough education under our belts now” to handle future issues.

Tennis, Anyone? Proposed Rink Delayed As Schools Seek Site For Varsity Courts [Video]

Photo: Belmont HS Juniors Brett Stievater and Phoebe Gray of the tennis teams seeking to bring back tennis courts to the new school campus.

After being delayed by more than six months due to concerns that the oversight process was too compressed, the anticipated solicitation of proposals for a new Belmont skating rink has again been put on hold as a last-minute appeal from supporters of Belmont High tennis has forced the School Committee to include five courts in the proposal.

The release of the request of proposal (RFP) for the new skating rink on school property west of Harris Field is now scheduled for Jan. 15, 2020 with the deadline for bidders to submit responses by Friday, March 20.

Additionally, the critical Town Meeting vote to approve the project and the transfer of the land for a public/private operation has been kicked from the first Town Meeting session in late April to the second night of the second session on June 1.

“There’s been an increasing call for the RFP to contain a programmatic need of tennis courts on the site and it finally came to a head,” said Jeffrey Wheeler, the town’s senior planner who is managing the RFP process.

The delay comes as the result of a last-minute push by a coalition of members of the high school tennis squads and racquet-loving residents who contend tennis was slighted in the design of the Belmont Middle and High School, the new 425,000 sq.-ft., $295 million school building that will house grades 7th to 12th.

While detailed plans for the new building and the land has been approved earlier in the year, the initial protest occurred when an army of supporters squeezed into the Chenery Middle School’s small conference room as if it was the Wimbledon grandstand before a championship final.

But the crowd of students, parents, and friends that came to the Belmont School Committee’s Nov. 12 meeting to express the collective unhappiness of their sport being ignored in the new school’s sports community.

“This is a simple question of equity,” said Katherine Stievater, a resident, parent of two varsity tennis players and boys’ tennis liaison to the Belmont Boosters Club.

“Members of the tennis team were disappointed and shocked when we learned that we’re the only varsity sport at Belmont High School that will not have its playing facilities rebuilt on the new campus,” said Belmont High Junior Brett Stievater who played varsity doubles last season.

The existing high school once had 10 courts near its east wing adjacent to the student parking lot, more than enough – five are required – to hold both the regular season and tournament matches.

But when the new school project was designed, it was discovered early on the building – which has a greater footprint than the existing building and roadways and parking – would put a squeeze on the playing fields surrounding the school. The solution was

Stievater noted that all other varsity teams will practice or play on the new campus

While the teams can use municipal courts to practice, that option will push residents off of playing surfaces that they have been using ,” said Donna Ruvolo, co-chairman of the Friends of Grove Street Park who was representing the municipal courts at the Grove Street Playground, adjacent to PQ Park and the Winn Brook Elementary School.

The campaigner’s support is wide and growing; petitions with several hundred signatures along with the support from the captains of each sports at the high school.

“It has been amazing to see other Belmont students support the tennis team being on campus. All varsity sports deserve to be represented on the new campus,” said Belmont High Girls’ Tennis representative Phoebe Gray.

“I think they know that it could have been them being sent off-campus,” said Gray.

While it appears movement has been made to restore the courts on school property, including those courts will likely force the schools to lose a playing field for other sports which it will be hard to replace, said Wheeler.

Wheeler noted the School Committee is planning to conduct a Community Impact Analysis which will determine the effect moving playing fields off-site will have for the students and other organizations such as Second Soccer. That analysis will. be completed by Jan. 7.

One longer-term hoped-for solution would occur with the construction of a pedestrian tunnel under the commuter rail tracks from Alexander Avenue to the high school campus, allowing for easier access for teams to the Winn Brook playing fields.

Belmont Middle And High School Is … On Budget!

Photo: In the black

After two misses in which the budget for the new Belmont Middle and High School recorded deficits of $30 million in April and $19 million in late August, it was with a bit of trepidation for the school’s Building Committee to hear the final budget estimate from the design team during the committee’s meeting on Tuesday night, Nov. 5.

With the development at the benchmark 90 percent of all bids, the project design budget was announced as being … in the black by $300,000.

Whew!

“This is excellent,” said Bill Lovallo, chair of the committee which this Friday will send a dense binder holding all of the project’s 1,300 drawings and financials to the Massachusetts School Building Authority, which is partnering with the town on constructing the $295.2 million, 451,575 square foot school.

“Our final estimated check says that we are on budget,” he told the committee, noting that the final figure was the average of three estimations from each of the design team; architect Perkins+Will, general contractor Skanska and owner’s project manager Daedalus.

Lovallo said he is confident that the remaining contingency funds – about $10 million – will protect the project against escalating costs or construction overruns. He also said that the design team is receiving an interest in the number of firms interested in bidding on the project.

With the budget appearing stabilized, the committee will return in two weeks to discuss possibly bringing back approximately a dozen or so items trimmed during the earlier value engineering dubbed the bid alternative process.

“We want a mechanism by which when we bid and the price has come in a little higher than we expected we have the ability to accept the bids and if they come in a little lower than expected, we could make adjustments to add things that we took out at 60 percent,” said Lovallo, who noted that already Skanska is currently finding additional cost savings in the construction of the school’s facade.

At the Nov. 21 meeting (at 7:30 a.m. in the Belmont Art Gallery in the Homer Building), the committee will take a pared down list of items and rank each item in the committee’s preference of being returned to the building project, ie. the item selected number one will be the first added back with any additional funds.

It’s likely most items on the list will seem mundane – such as tiles and ceiling panels – but they have been identified by several committee members as important components to the educational goals and to the appearance of the school.

A popular item to bring back is the orchestra pit whose campaigners came out to support before the committee last month. Solar power advocates continued their public participation to hold the committee to earlier commitments to keep solar arrays in the building program, although Lovallo said the arrays will not be on the Nov. 21 list since it will likely one of the very last items bid in three years time.

Arrays Away? Move To Delay Solar Panels From New HS Project As Critics Seek To Prevent $3M In Cuts

Photo: The Belmont Middle and High School Building Committee, residents and the design teams at the Sept. 20 meeting.

A move to eliminate the installation of solar arrays on the roof of the new high and middle school building currently under construction is gaining momentum as the Belmont Middle and High School Building Committee is making tough cuts to save $19.2 million in cost overruns at the $295 million project.

The Sept. 20 gathering of the Building Committee was the third of four meetings dedicated to value engineering in an attempt to trim about nine percent of the anticipated expenses in the project. And the team select to find those savings – made up of the project’s design and construction teams; general contractor Skanska, architects Perkins+Will, and project manager Daedalus – came up with $19.5 million in both recommended cuts ($17.6 million) and those savings that needed further discussion ($1.9 million) before being removed from the budget. In addition, the team has pointed to nearly $6.4 million in expenses that could be rebid for possible additional savings.

The reduction in expenses are coming from the building’s exterior and interior, the systems, the site and structure and phasing and logistics. Some examples of the 70 items selected range from reducing the number the granite curbs on the site to the entrances and drop off locations ($101,100), electrical system savings ($105,000), simplify floor finishing and construction ($77,500) and reducing from two to one wall of marker boards in classrooms ($157,200).

As the committee members were discussing the design team’s recommendations on the possible cuts, committee member Bob McLaughlin interrupted the process to question why one of the largest expenses was not on the chopping block.

At $2.9 million, the photo-voltaic panel system – the solar panels on the building’s roof – is easily the costliest of big-ticket items up for consideration, which the design team said could be re-bid with the expectations that a new price tag for the panels would likely be in the $2.3 million range.

But even a reduction of $600,000 leaves too much in the budget, said McLaughlin. “We should take it away now,” said McLaughlin of the arrays. In McLaughlin’s view, the school’s first-class building was being downgraded to a second rate structure, calling it “a death by a thousand cuts.”

With the school’s expected life span of 50 years, it is incumbent that as much of the systems and interior designs be kept, said McLaughlin. If they are take off at this stage “we’ll never get a chance to [do bring it back in the future.]”

“I want these items we are giving up tonight back in,” said McLaughlin, referring to such expenditures as skylights in the high and middle school wings ($208,000 total) and wall tiles in the locker rooms ($157,300).

McLaughlin said he is not opposed to solar panels in fact, he believes by waiting three to five years after the building is opened would be financially advantageous. While most aspects of construction have been increasing in price in the past two decades, solar panels are seen a steady decrease in cost, dropping more than 60 percent between 2008 and 2018.

McLaughlin said after the meeting that the cost of $1.5 million for panels purchased in the mid-2020s which the town could purchase with a bond offering.

“Let’s bite the bullet now. Let’s take [the panels] off,” he said, recognizing the possibility of a political backlash with its move.

McLaughlin’s comments would be been a one-off sound off but for who joined his view.

Belmont’s chief educational official, Superintendent John Phelan, said “at the risk of sounding controversial” while he will be proud of a “green” school “but there is a priority list in my head … such as whiteboards which are teachable school programs that [the committee] said we would prioritize.”

And while having low operating costs in energy is an advantageous goal, by substituting lesser materials – in such places as flooring or stairs – the committee is creating long-term maintenance issues.

“We made a commitment to the town to build a quality school that will last a few years. There’s a lot of layers to that,” he said, adding that it’s good to have the conversation on items just as important as solar panels which has sizable support.

“There are other items that don’t have a constituency that really aren’t highlighted. No one talks about tiles on the first day.

‘An Awful Lot Of Money’

Phelan was followed immediately by Steve Dorrance, the town’s facility manager, who said that “no one is going to look up at the roof and say ‘don’t those PV panels look wonderful.”

“What you will do is walk through the school in five years and ask, ‘Why does the school looks the way that it does?’” Dorrance said, adding when the certainty of funding the retrofitting of the building goes before the public, “it will be a striking uphill fight.”

“It’s an awful lot of money that we can save now by putting back the $30,000 or $20,000 items. We can do a lot of those items for $3 million,” said Dorrance.

A possible removal of the panels would be a reversal of what the committee acknowledged was one of three main goals in designing the school was to construct a Net Zero Energy facility. In fact, during an initial value engineering discussion in May, the committee faced a roomful of solar supporters who demand the arrays be a priority and protected from cuts.

A small number of observers from the town’s Energy Committee and members of Sustainable Belmont attending last week’s meeting said the savings to the town – $5 million over 30 years – is well worth the upfront expense. They also pointed to town meeting votes that repeated supported a climate action plan that promotes solar and alternative energy in municipal structures.

Energy Committee’s Jacob Knowles said solar is a core element to the new school. He said the savings in energy costs could be used to fund the necessary maintenance to the building to keep the systems up to date.

“[Solar] is the smartest financial choice of the whole project with the most net cash flow relative to the investment on anything on this building,” said Knowles.

But two additional comments from committee members appeared to give the opponents to hold back on fitting solar panels during the school’s construction stage.

Town Administrator Patrice Garvin said since the building will either have arrays or not, the ultimate question is what is the annual cost difference between the school’s projected energy costs with and without the solar panels. With modern building controls, the latest window designs and other energy systems such as geothermal, the cost difference between the two outcomes could well be negligible to the committee members.

In addition, Committee chairman Bill Lovallo said the Massachusetts School Building Authority, which is partnering with the town in constructing the school, has requested the building committee attend a review of the project expenses. “We are being sent to the principal’s office,’ said Lovallo, to explain the committee’s value engineering process.

Lovallo said the MSBA has a “hard and fast rule” that any expense reduction exercise at buildings under construction doesn’t compromise the schools educational program, a point reiterated by Phelan in his defense of discussing the delay of fitting the solar arrays on the school’s roof.

However the solar panel discussion is resolved, it will need to be concluded at the committee’s next meeting, tentatively scheduled for Thursday morning, Sept. 26, at 7:30 a.m. in the Homer Building.

“We have to make a decision on all these cuts [then],” said Lovallo.

First Day Of School Goes To Plan As Key Construction At High School Site Nears Midpoint

Photo: A third of the piles have been installed in phase one of the Belmont Middle and High School project.

It was a long Wednesday, Sept. 4 for Belmont Superintendent John Phelan.

After a busy Tuesday welcoming teachers and staff back to the district after the summer recess, Phelan’s Wednesday began bright and early at Belmont High School where he joined staff and Belmont Police in a new role, as traffic monitors to assist students and parents with the first new parking and drop off scheme since the school opened 49 years ago in 1970.

With the access road which once allowed parents to drop off students at the high school’s main entrance before exiting onto Concord Avenue now a fading memory, cars, SUVs and minivans clogged Underwood Street before doubling back onto Hittinger Street and out through the Trowbridge neighborhood due to the large scale construction of the new middle and high school at the west end of the project.

But with so much that could go so wrong, opening day of the 2019-2020 school year went “very, very well,” said Phelan during the meeting of the Belmont Middle and High School Building Committee on Wednesday.

“The wait … was not too long into the [high] school” due in large part to the team of officers from the Belmont Police along with signs produced by the Department of Public Works and balloons used to identify where vehicles could come and go.

“It was good to see the kids back at school,” said Phelan, who when not running a school system of 4,200 students was also tasked with supplying the Building Committee with pizzas and drinks.

“All in a day’s work,” he said pushing a chart into the Homer Building.

While the work of bringing a new class of 9th – 12th graders, the largest and largest construction task to date is moving along quickly as 133 concrete piles have been driven into the ground to anchor the high school wing of the building. Just on Wednesday, 27 “corner” piles were secured, marking out the rough outline of the high school section, according to Mike Morrison, project manager for Skanska, the general contractor.

“We are one-third of the way in Phase 1 of the building,” said Morrison, noting that debris and soil is being removed from the site as construction beginning in and around the site of the school’s pool.

“All is going well,” said Morrison.

Report: Turf Bests Grass For High School Field; See Why At Public Meeting Wed., Aug. 21

Photo: A close up of the artificial turf at Harris Field.

A comprehensive “fact-based” report by a member of the Belmont Middle and High School Building Committee recommends the group move forward with the construct of a new artificial turf ground known as the “Rugby Field” adjacent to the Wenner Field House.

The study’s conclusions will be featured in a grass vs. artificial turf discussion at a public meeting being held by the Belmont Middle and High School Building Committee on Wednesday, Aug. 21 at 7 p.m. at the Beech Street Center, 266 Beech St.

Authored by Robert “Bob” McLaughlin, the report concludes that turf’s greater capacity to withstand year-round use and the field’s location in a shady corner of the new school necessitates building a turf ground instead of a grass field.

While a growing number of Belmont residents and parents of students are raised concerns that turf fields are connected to serious health and safety issues including alleged increase in cancer rates for certain athletes, McLaughlin reported that independent research overwhelming concludes there are no proven detrimental health effects from playing on artificial fields.

The field, to be built in 2021, will be used by the state champion boys’ and girls’ rugby programs, as a practice and playing site for sub-varsity sports and for three-seasons of physical education classes.

The natural grass playing surface at Grove Street which includes a line of clovers.

The Building Committee’s Chair Bill Lavello said McLaughlin, and School Committee Member Katie Bowen will speak on the issue before the public comments on the findings.

In his 35-page report, McLaughlin started by stating the obvious: Belmont doesn’t have enough playing fields to meet the demands of school teams and the town’s recreational programs with grounds crowded with school and club teams year-round. Currently each town field is used on average 482 hours in the spring and 290 in the fall above the advised limit of 250 hours each season to avoid stress and deterioration.

The town has pointed out in the past the expense of maintaining a healthy football/soccer-sized grass field at upwards to $100,000 annually as well as the loss of playing space as natural surfaces need to be “put to bed” for the following playing season (in the spring if games are played during the fall) to allow the grass and top soil to recover.

The school district’s Athletic Director Jim Davis noted to McLaughlin that turf fields can be used more often, require less maintenance and can be used by many sports without a loss of field consistency.

McLaughlin points to “many … studies” suggesting turf fields can be used “three times” more than natural grass without the wear and tear placed on a nature surfaces.

“The flexibility and increased usage available with artificial turf is vital to maintaining an acceptable athletic program for the now-expanded grades 7-12 enrollment on our limited school campus,” McLaughlin said.

But it is alleged health concerns to young adults and children that prompted the committee to request the study. The report was commissioned in June after a group of residents questions the safety of artificial grass playing ground at the school and in town.

McLaughlin acknowledge the worries from residents and people that turf fields are allegedly linked to cancer threats from the rubber infill – the small round pellets known as crumb made of ground tires – used in the majority of the 13,000 synthetic athletics fields across the US.

Yet McLaughlin could not find any evidence “in the plethora of studies” he researched that links the infill – which McLaughlin noted contains known carcinogens – to increased cancer rates among players who use the turf fields.

He added that just last month, the US Environmental Protection Agency issued a final report of a multi-agency study (dubbed the Federal Research Action Plan on Recycled Tire Crumb Used in Playing Fields and Playgrounds or FRAP) that concluded while chemicals are present in the crumb rubber, “human exposure appears to be limited on what is released in the air or simulated biological fluids.”

There are alternatives to rubber infill such as a cork and coconut mixture and quartz-based sand. Yet each has its own issues: the cork/coconut mix will “freeze” on the first fall frost and has a higher rate of abrasion injuries while field operators question whether commercial sand can stand up to a field under continuous use.

McLaughlin countered some of the health concerns by noting that physical activity during adolescence and early adulthood helping prevent cancer later in life and leading to a reduction in cardiovascular ailments.

While further studies assessing individual-level exposure is needed, [U]ntil then, however physical activity should be encouraged and promoted by year-round, weather resistant fields,” said McLaughlin.

Second, on the list of issues is elevated temperatures produced by a turf field, increasing temps 20 to 40 degrees F. Critics contend the super-hot grounds could prove a serious health condition especially for younger players.

Athletic Director Davis has informed town officials the “cushion” the turf lies on is coated white, which absorbs a great amount of the heat. Davis noted the overwhelming injury concerns at Harris Field are from possible concussions and ligament damage rather than heat. In addition, most high school practices occur after 3 p.m., once the hottest part of the day has passed.

Some residents who are opposed to artificial turf have expressed their goal of not just stopping the high school’s second turf field but also taking out the small field at the Wellington Elementary School and reverting Harris Field to natural grass when the current artificial turf is retired with the next decade.

Support for natural surfaces is growing around town. A few residents who attended a July public meeting on placing temporary lights at two town playing fields to support Belmont Youth Soccer said they would not allow their children to play high school sports due to the artificial turf surface.

Those health warnings associated with artificial turf prompted Connecticut legislators to sponsor a bill that would prohibit towns and school districts from installing new artificial fields. The measure remains in a legislative committee.

At a meeting last month, the Belmont Board of Health stated it may need to weight in on the matter.

It is not known if the Building Committee will vote after the discussion Wednesday on moving forward with a specific surface.

Bang! Bang! Bang! Pile Driving At High School Starts Tuesday, Aug. 20

Photo: Pile driving set to start on Tuesday.

Get ready, Belmont. Beginning early next week, the neighbors living near the Belmont Middle and High School construction site will soon be listening to 10 hours a day of “the rockinest, rock-steady beat” of pile driving madness.

That’s the word from Skanska, the project’s general contractor, which announced the long awaited installation of the underpinnings of the new school’s foundation at the Belmont Middle and High School Building Committee meeting on Tuesday, Aug. 13. The foundation will require a few hundred piles (essentially poles) to transfer the large building loads to the earth farther down from the surface.

According to Project Manager Mike Morrison, the pile driving team will be onsite by Friday, Aug. 16 with the actual installation of the first of the 80 foot piles beginning on Tuesday, Aug. 20.

And the pounding will be a constant for residents and students for the next months. The steady beat of the drill pounding away on the site will run from 7 a.m. to 5 p.m., Monday through Friday.

In addition, due to state regulations on the transportation of extremely long piles on highways, residents can expect deliveries traveling on town streets from 6 a.m. to 7 a.m.

Just how long will the steady beat of piles being driven deep into the soil? Morrison would only say the work will continue “through the fall” with no specific end date.

And it will be loud. According to data from the American Speech-Language-Hearing Association, the noise produced when the anvil strikes the strike plate on the pile can generate noise as much as 135 dB, which is somewhere between jackhammer and a jet engine. Even 200 feet from the source, the noise can reach 68 dB.

For some, the vibration and noise can be too much. On the website SeeClickFix.com, the pile driving conducted at the former Lane & Games bowling alley off of Route 2 in North Cambridge a year ago brought a torrid of complaints from Arlington and Cambridge residents.

“Like you, we’re pretty annoyed by hearing it start up every morning in the distance, like the Excedrin headache from @#$%,” wrote David S.

The work will begin close to the school than move outward towards Harris Field and the intersection of Concord Avenue and Goden Street. Prior to the work starting, owners of 43 of approximately 76 residential structures signed up to have the exterior of their properties examined.

John Phelan, Belmont Schools Superintendent, said he and Isaac Taylor, the High School’s new principal, will be on site when the pile driving begins to monitor the noise level. But he doesn’t believe the noise or vibration will affect learning as students are adept at attending classes with up to seven MBTA commuter trains rumble adjacent to the school.

Belmont Town Administrator Patrice Garvin said residents will be provided a heads up on the start of the job via the police department’s “reverse 911” system.