Photo: The newest school building in Belmont.
After nearly 27 months of construction, tons of steel, concrete, wires and piping, and a lot of money, the (nearly) completed high school wing of the new Belmont Middle and High School is now in the hands of the Belmont School Committee after the town issued the committee a temporary certificate of occupancy on Aug. 31.
”Belmont has much to be proud of,” read the letter accompanying the certificate to the school district. (See the letter below)
“The building project has been in the ownership of Skanska construction and the building committee since it started digging into the ground several years ago,” Belmont Superintendent John Phelan told the School Committee on Tuesday, Sept. 7, two days before the opening day of the 2021-22 school year as well as the first day the high school section will be open to students.
The committee voted unanimously to formally accept the TCO.
Phelan noted that several town departments including Police, Fire, and Health had to sign off on the certificate to allow the ownership transfer to the School Committee. It will remain a temporary certificate until the 7th and 8th grade middle school wing is completed in Sept. 2023 and the permanent certificate will be issued. The now former high school building, opened in 1970, is being demolished.
As of August, 2021, 54 percent of the construction has been completed with $166.5 million spent out of the $295.2 allocated to the project.